Painting the interior of a flat, changing its layout and replacing window frames are subject to different rules. Some works are exempt from both a building permit and prior notification, but you may still need to inform the municipal council before work begins. The applicable procedure depends on the property’s location, the nature of the work and its effect on the building. Portugal’s Legal Framework for Urban Development and Building (RJUE) was revised by Decree-Law No. 108/2026, with changes in force since 1 October 2026. Articles 6 and 6-A set out the main exemptions, while Article 80-A governs the notice of commencement of works. RJUE, consolidated version · Portugal’s Simplex Urbanístico 2026: what changed in building permit rules

Which works are exempt from a building permit and prior notification?

Article 6 of the RJUE covers the following works, among others. Whether an exemption applies depends on the statutory conditions and any heritage protections affecting the property.

  • Maintenance and repair works. These are works that keep a building in its existing condition, such as painting the interior or repairing deteriorated cladding using the same finish. Maintenance and repair works carried out entirely inside a building or unit are exempt from the notice of commencement if they fall under Article 6(1)(a).
  • Internal alterations to buildings or individual units. An exemption may apply if the work does not entail external changes that affect the building’s physical or aesthetic characteristics, notably its height, façades, roofs or roof coverings. If the works affect structural stability, a structural design, a declaration of responsibility signed by a qualified professional and, where required, a seismic strengthening design must be prepared. The professional must declare that the works as a whole improve or preserve the building’s structural stability compared with its previous condition. The documents are filed with the municipal council along with the notice of commencement.
  • Reconstruction works. The exemption applies to reconstruction as defined in the RJUE, taking the property’s most recent valid planning record as the reference and reinstating the composition of the façades and roof as required by law. If the proposal increases the floor area or volume, check the rules that apply to extensions.
  • Works of minor planning significance. These include small structures and other works listed in Article 6-A, as well as works that municipal regulations designate as such.

Article 6 also covers specific cases, including certain works ordered by the municipality, the demolition of unlawful structures and development proposals that have received a favourable decision on a Prior Information Request (Pedido de Informação Prévia, or PIP) under Article 14(2), where the decision covers all applicable elements. In the latter case, the exemption applies to the proposal as assessed, excludes use or change of use, and is subject to specific requirements before work begins. RJUE, Articles 2, 6, 14, 17 and 80-A · Prior Information Requests: types and legal effects

What counts as works of minor planning significance?

Article 6-A of the RJUE sets out the following cases. Municipal regulations may designate other works as being of minor planning significance and set additional limits for small structures, walls and greenhouses. RJUE, Article 6-A

Type of workConditions to check
Small structure associated with the main buildingAn area of up to 10 m². The structure must not adjoin a public road. It may be attached to or separate from the main building. The maximum height is 2.2 m or, alternatively, the height of the main building’s ground floor.
Boundary walls and retaining wallsBoundary walls may be up to 1.8 m high and must not adjoin a public road. For retaining walls, the law specifies a maximum height of 2 m or requires that the existing topography remain substantially unchanged.
Garden greenhousesLess than 3 m high and up to 20 m² in area.
External improvements and recreational facilitiesMinor improvements around buildings must leave public land unaffected. Recreational facilities must be associated with the main building and occupy a smaller area than that building. The law also covers the demolition of structures specified in the provisions preceding Article 6-A(1)(f).
Solar panels, solar thermal collectors, energy storage and small wind turbinesPhotovoltaic panels must stay within the roof area and may extend up to 1 m above the building’s height. Solar thermal collectors and energy storage units are subject to the same limits, and any tank or water or energy storage unit must be concealed. Wind turbines may extend up to 4 m above the building’s height, with a radius of up to 1.5 m. They require specific notification to the municipal council.
External cladding and roof coveringsReplacement with materials that improve energy efficiency may qualify for an exemption if the external finish remains identical to the original.
Replacement of window framesThe new frames must improve energy efficiency while retaining the original geometry, the proportions between components and an external finish identical to the original.

What rules apply to protected heritage?

As a rule, Article 6-A excludes works and installations affecting listed properties or properties under consideration for listing, properties within listed ensembles or sites or those under consideration for listing and properties within the associated protection zones. Replacement window frames in protection zones may qualify for the exception under Article 6-A(1)(j) if they meet its conditions. RJUE, Article 6-A(1) and (2) Article 6 also provides an exception for maintenance and repair works on listed properties, properties under consideration for listing and properties within ensembles or sites with either status. These works may be exempt if they receive a favourable opinion from the relevant cultural heritage authority. Submit that opinion with the notice of commencement. Removing façade tiles is subject to specific provisions under Article 4 and requires a permit. RJUE, Articles 4 and 6

Do I need to tell the municipal council before starting exempt works?

In most cases, yes. Article 80-A requires the project promoter to inform the municipal council no later than five days before work begins, identify who will carry out the works and provide the required documentation. In cases covered by Article 80-A(5), the law also requires a notice to be displayed on site where it can be seen from the public road. The notification and the site notice use the templates established by Ministerial Order No. 320/2026/1. The exception to the notice of commencement covers maintenance and repair works carried out entirely inside buildings or individual units under Article 6(1)(a). A refurbishment that changes the internal layout should be assessed as an alteration, even if it leaves the structure intact. RJUE, Articles 2, 6 and 80-A · Ministerial Order No. 320/2026/1

What we check before work begins at MJARC

When planning a refurbishment, we start by looking at what the proposed work will change. A wall that appears to be a simple partition may carry structural loads. A window with better thermal performance may change the appearance of the façade if its frame profiles or proportions change. Identifying these effects early helps us decide what to preserve, which designs to prepare and when to involve the municipality. Even where an exemption applies, spatial plans, municipal regulations, easements and restrictions, technical standards and heritage protection rules still apply. The works may also be subject to inspection. RJUE, Article 6(8) If you are planning building works, send us the property’s location, some photographs and a brief description of what you have in mind. This information helps us start assessing which rules apply and what documents you may need. Contact the MJARC team

Frequently asked questions

Can I remove an internal wall without a building permit?

An alteration carried out entirely inside the building may be exempt. Before removing the wall, establish whether it contributes to the building’s structural stability. If it does, check the conditions in Article 6 and prepare the required designs and declarations to submit with the notice of commencement. RJUE, Article 6(1)(b)

Can I convert a shop into a home if the works are exempt?

A change of use is subject to its own rules. The procedure depends, among other factors, on any works that precede the change. The RJUE sets out different formalities in Articles 62-A and 62-B. Check whether residential use is permitted at the property. RJUE, Articles 4, 62-A and 62-B

Is a 10 m² outbuilding always exempt?

The 10 m² limit is only one of the criteria. Also check the height, the relationship to the main building and the public road, local regulations and any restrictions affecting the property. RJUE, Article 6-A